Endeavour Silver Produces 1st Batch of Concentrate at Terronera Mine, on Track for Wet Commissioning in Early Q2

  • Facebook.
  • Twitter.
  • LinkedIn.
  • Print

06:13 AM EDT, 04/01/2025 (MT Newswires) -- Endeavour Silver ( EXK ) late on Monday provided a construction progress update for its Terronera project in Mexico, which is in its final construction stages.

Wet commissioning is expected to start early in the second quarter, the company said. The crushing, grinding, flotation and tailing thickening circuits successfully ran to produce over two tonnes of concentrate. The upper platform process plant commissioning is well advanced and concentrate filter pre-commissioning has started. The tailing filter mechanical assembly was also completed.

The tailing storage facility main embankment has reached full height, and the underdrain piping with gravel cover has been installed and prepared for life of mine tailing placement. The first production stope has been mined and backfilled. Surface run-of-mine and crushed ore stockpiles have reached 40,000 tonnes.

The company is focused on completing the tailing filter electrical and mechanical installations and the pipeline connections between the upper and lower platforms.

MT Newswires does not provide investment advice. Unauthorized reproduction is strictly prohibited.

© 1999-2025 Midnight Trader, Inc. All rights reserved.

  • Facebook.
  • Twitter.
  • LinkedIn.
  • Print
close
Please enter a valid e-mail address
Please enter a valid e-mail address
Important legal information about the e-mail you will be sending. By using this service, you agree to input your real e-mail address and only send it to people you know. It is a violation of law in some jurisdictions to falsely identify yourself in an e-mail. All information you provide will be used by Fidelity solely for the purpose of sending the e-mail on your behalf.The subject line of the e-mail you send will be "Fidelity.com: "

Your e-mail has been sent.
close

Your e-mail has been sent.