Endeavour Silver Produces 1st Batch of Concentrate at Terronera Mine, on Track for Wet Commissioning in Early Q2
Wet commissioning is expected to start early in the second quarter, the company said. The crushing, grinding, flotation and tailing thickening circuits successfully ran to produce over two tonnes of concentrate. The upper platform process plant commissioning is well advanced and concentrate filter pre-commissioning has started. The tailing filter mechanical assembly was also completed.
The tailing storage facility main embankment has reached full height, and the underdrain piping with gravel cover has been installed and prepared for life of mine tailing placement. The first production stope has been mined and backfilled. Surface run-of-mine and crushed ore stockpiles have reached 40,000 tonnes.
The company is focused on completing the tailing filter electrical and mechanical installations and the pipeline connections between the upper and lower platforms.
MT Newswires does not provide investment advice. Unauthorized reproduction is strictly prohibited.
© 1999-2025 Midnight Trader, Inc. All rights reserved.

Related News
-
Quoin Pharmaceuticals Changes ADS Ratio to Meet Nasdaq Rule
MT Newswires - 26 minutes ago
-
GameStop Says Nintendo Switch 2 US Pre-Orders to Be Delayed on Tariffs Review
MT Newswires - 26 minutes ago
-
Sotera Health's Sterigenics to Pay Nearly $31 Million to Settle Ethylene Oxide Claims in Illinois
MT Newswires - 30 minutes ago
-
Resmed Insider Sold Shares Worth $439,480, According to a Recent SEC Filing
MT Newswires - 32 minutes ago
-
Neurocrine Biosciences Appoints New Chief Medical Officer
MT Newswires - 40 minutes ago
-
ISS recommends votes against Bank of America's CEO pay
Reuters - 42 minutes ago
-
ISS recommends votes against Bank of America's CEO pay
Reuters - 47 minutes ago